Hoopa Valley Indian Reservation, Northern CA — The Hoopa Valley Public Utilities District (HVPUD) will begin construction on the SB156...
thanks to a limited-time construction project, acorn connected can install high-speed fiber to your home or business for free. please note: while the fiber installation is free, internet service is not.update
Stay up to date on construction progress, traffic alerts, and project milestones for the SB156 and NTIA broadband builds. Check back regularly or sign up for email updates.

Hoopa Valley Indian Reservation, Northern CA — The Hoopa Valley Public Utilities District (HVPUD) will begin construction on the SB156...

Hoopa Valley Indian Reservation, Northern CA — The Hoopa Valley Public Utilities District (HVPUD) is pleased to announce that the...
SB156 Middle Mile: GRC will be working in the area north of the big bridge (Hoopa Valley Shopping Center).
NTIA Project: TCDC will be working along Tish Tang Rd on the south end and also continuing along the Community Service Rd area.
11/17/25 – Construction Update
NTIA Project: Crews continuing work along Tish Tang Road and Carpenter Lane areas. Additional activity will focus on completing laterals near the gas station at Highway 96 and Legion Way.
SB156 Middle Mile: Crews will continue progressing south along Highway 96 from Weitchpec.
11/10/25 – In addition to ongoing construction at the north end of Highway 96 near Mile Post 22.7, crews are continuing work in the Carpenter Lane and Mill Creek areas. Work is also progressing along Tish Tang Road toward Community Service Road as part of the NTIA Fiber-to-the-Home Project.
11/03/25 – Crews are continuing work in two areas this week:
NTIA Project: Crews are continuing work in the Carpenter Lane area. Construction will also begin along Tish Tang Road, starting near Community Services Road and moving south.
SB156 Middle Mile: Glass Roots Construction crews will continue moving north along Highway 96, progressing through the next section of the route.
10/27/25 – Crews are continuing work in two areas this week:
NTIA Project: Ongoing fiber installation in the Mill Creek Rd and Carpenter Ln areas.
SB156 Middle Mile: Crews are working north along Highway 96.
10/13/25 – Crews working on the Last Mile Job are currently in the Mill Creek Road area and may move toward Carpenter Lane by the end of this week. Crews are also continuing work north along Highway 96 near Hoopa Valley High School. We’re doing our best to minimize traffic disruptions, especially during school drop-off and pick-up times.
10/06/25 – Construction off Hwy 96 in the vicinity of Marshall Lane area and Mill Creek Road. Expect delays up to 15 minutes.
9/10/25 – Construction on Hwy 96 at mile marker 9.1. Expect delays up to 15 minutes.
9/08/25 – Construction on Hwy 96 at mile marker 10, then continuing south toward Mile Marker 9. Delays up to 15 minutes.
7/31/25 – Construction on Hwy 96 at mile marker 0.1. Delays up to 15 minutes.
7/08/25 – Construction Begins July 8 on SB156 Middle Mile Project
Construction will begin for the SB156 Middle Mile Project on Tuesday, July 8, 2025. This historic collaboration between HVPUD and the State of California marks the first joint broadband build between a Tribe and the state.
WHERE: Highway 96, starting at mile marker 0.5, proceeding north
DELAYS: Expect up to 15 minutes as crews work to safely install underground fiber optic cable.
Construction will continue throughout the summer, moving in segments from Willow Creek to Weitchpec.
This project will bring high-capacity fiber infrastructure to the Hoopa Valley Indian Reservation and surrounding tribal lands, laying the groundwork for future broadband services.
The Hoopa Valley Public Utilities District (HVPUD) will begin construction on the SB156 Middle Mile Project on.
The Hoopa Valley Public Utilities District (HVPUD) will begin construction on the SB156 Middle Mile Project on.
The Hoopa Valley Public Utilities District (HVPUD) will begin construction on the SB156 Middle Mile Project on. Read More
Construction will begin for the SB156 Middle Mile Project on Tuesday, July 8, 2025. This historic collaboration between HVPUD and...